Scott schedule
Scott schedules (sometimes referred to as ‘official referee schedules') were originally developed by George Alexander Scott, a surveyor and official referee, for use in building disputes. They are now commonly used for a variety of legal cases that involve complex arbitration where there are numerous claims, including; property law, family law, employment tribunals and so on.
A Scott schedule is essentially a table with inputs from both the claimant and respondent. Typically the claimant will set out their argument first, then the schedule is passed to the respondent to set out their response. This requires a degree of collaboration between the parties.
In the event that the dispute reaches the courts, the final column in the schedule is provided for the judge to give their decision against each item.
The Technology and Construction (TCC) describes a Scott schedule as ‘…a table, often in landscape format, in which the Claimant’s case on liability and quantum is set out item by item in the first few columns and the Defendant’s response is set out in the adjacent columns’ (TCC, Court Guide). They suggest it is suitable for ‘...claims involving a final account or numerous alleged defects or items of disrepair’ and that ‘…even where all the damage has been caused by one event, such as a fire, it can be helpful for the individual items of loss and damage to be set out in a Scott Schedule.’
The TCC suggests that the power of Scott schedules is in the information provided and their brevity, proposing that excessive repetition should be avoided. The response should be clear and specific, dealing with each issue and providing statements that make clear which claims are admitted or agreed, which are denied and why. More detailed explanations may be given in statements and in evidence in court.
A Scott schedule may be prepared by agreement by the parties (for example in a terminal dilapidations claim) or may be ordered by the court, in which case the judge may give directions for the relevant column headings. This is likely to include; the claim, the cost, the response, an alternative figure and the judge’s decision (see RICS, Example of a Scott schedule).
Scott schedules should only be used where they will lead to a saving in cost or time and where they are appropriate and proportionate.
In the case of a dilapidations claim, a Scott schedule may be an extended version of a schedule of dilapidations prepared by the landlord, enabling the tenant to respond to the quantified demand.
NB Dilapidations in England And Wales, 7th Edition, was published on 31 August 2016 by the Royal Institution of Chartered Surveyors (RICS), it defines a Scott Schedule as: ‘a Schedule of Dilapidations with additional columns to enable the parties to set out their respective views. The document is usually prepared by a building surveyor.’
[edit] Related articles on Designing Buildings
- Alternative dispute resolution.
- Betterment.
- Break clauses in leases.
- Defects.
- Dilapidations.
- Dilapidations protocol.
- Final account.
- Disputes.
- Lease Negotiations - Tenants Checklist.
- Licence for Alterations for Apartment.
- Quantified demand.
- Rent-free period.
- Rent in administration.
- Rent review.
- Schedule.
- Sample retail lease.
- Schedule of dilapidations.
- Supersession.
[edit] External references
- TCC, Court Guide Second Edition Issued 3rd October 2005, third revision with effect from 3 March 2014, HM Courts and Tribunals Service.
RICS, Example of a Scott Schedule.
Featured articles and news
A case study and a warning to would-be developers
Creating four dwellings... after half a century of doing this job, why, oh why, is it so difficult?
Reform of the fire engineering profession
Fire Engineers Advisory Panel: Authoritative Statement, reactions and next steps.
Restoration and renewal of the Palace of Westminster
A complex project of cultural significance from full decant to EMI, opportunities and a potential a way forward.
Apprenticeships and the responsibility we share
Perspectives from the CIOB President as National Apprentice Week comes to a close.
The first line of defence against rain, wind and snow.
Building Safety recap January, 2026
What we missed at the end of last year, and at the start of this...
National Apprenticeship Week 2026, 9-15 Feb
Shining a light on the positive impacts for businesses, their apprentices and the wider economy alike.
Applications and benefits of acoustic flooring
From commercial to retail.
From solid to sprung and ribbed to raised.
Strengthening industry collaboration in Hong Kong
Hong Kong Institute of Construction and The Chartered Institute of Building sign Memorandum of Understanding.
A detailed description from the experts at Cornish Lime.
IHBC planning for growth with corporate plan development
Grow with the Institute by volunteering and CP25 consultation.
Connecting ambition and action for designers and specifiers.
Electrical skills gap deepens as apprenticeship starts fall despite surging demand says ECA.
Built environment bodies deepen joint action on EDI
B.E.Inclusive initiative agree next phase of joint equity, diversity and inclusion (EDI) action plan.
Recognising culture as key to sustainable economic growth
Creative UK Provocation paper: Culture as Growth Infrastructure.






















Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.